Toka Tindung is a gold mining project located at North Minahasa, North Sulawesi, Indonesia. PT ODG Indonesia contributed as the main Electrical, Instrumentation contractor for the project

 

2011 – Supply & Installation of the electrical and instrument for the process. Various electrical upgrade in new mill and KV over head land 

2018 – Toka Tindung Plant Expansion Project – Air Conditioning/ Fire Alarm/ Electrical.

2015 – Electrical Installation for Toka Tindung Permanent Power Supply Package-2 – Electrical.

2015 – Toka Tindung Permanent Power Supply Substation Building – Electrical.

2011 – Supply and Installation of Electrical & Instrumentation Toka Tindung Project – Instrumentation/ Electrical.

2011 – Toka Tindung Gold Mine Overhead Transmission Lines (11 KV) – Electrical.

2019 – Upgrade power network from 11,000 volts to 33,000 volts